Building a Backyard Deck | Costs so far: | ||||||||||||||||||||||||||||||||||
| Zach's Page Kelsi's page Bayla's Page Dreamer's page Our home Photo albums Reviews Our adventures Vehicles Computer Stuff • Tivo • Home Network
|
1.
layout & design
(March28th)
2.
digging
(April 9th)
3.
digging
(April 11th)
4.
permits/design/lumber
(April 14th)
5.
concrete footings
(April 25th)
6.
final footings
(May 12th)
7.
Install ledger
(May 13th)
8.
Deck Framing (finally!)
(May
15th)
9.
more framing
(May
16th)
10.
more framing
(May 17th-18th)
11.
final framing/flashing
(May 19th)
12.
Decking
(May 20-31st)
13.
Posts / south stairs
(June 1st)
6/1/04 Today was a great day in the deck building process! With Kelsi's help, I was able to get 4 posts up. I also finished up the stairs on the south side of the deck. All I need now is to install a handrail for them. The south stairs now have risers behind them to hide the ugly pressure treated framing. I only have 7 posts to go! WooHoo...then it's time to build the railings and install the lighting and rout out the drink holders :-) here's some pictures:
|
|
|||||||||||||||||||||||||||||||||